Ardent Mills Grain Terminal Project

A tall concrete grain elevator with multiple cylindrical silos stands against a clear blue sky. Vertical conduit lines run up the center of the structure to a small white utility building at ground level, which is enclosed by a chain-link fence.

Project Specifications

A blue line icon of an industrial facility with two smokestacks, representing a manufacturing plant or processing facility. Commonly used to symbolize value-added agriculture or industrial operations.

Industry

Grain Receiving & Storage Terminal

bar chart with magnifying glass focused on a dollar symbol icon

Dollar Amount

$3,900,000

A blue icon showing a checklist with three checkmarks next to a clock face, representing time management, scheduling, or tracking progress over time.

Completion Date

2026

location icon

Location 

Wichita, KS

See This Resource

Ardent Mills partnered with Interstates to modernize the electrical infrastructure at their grain terminal facility in Wichita, Kansas—replacing aging equipment and improving overall system reliability and safety for both personnel and operations. Through a phased approach, the project establishes a new electrical room and installs ethernet-enabled MCCs while automating motors across the facility, allowing each portion of the plant to transition without disrupting ongoing production. Once complete, the upgrades will deliver a fully automated system that not only improves operational efficiency but also simplifies plant operations as workforce transitions occur.

Services Provided: Electrical Construction | Electrical Engineering | Industrial Automation | Instrumentation | Panel Fabrication | Prefabrication

Key Scope Components

Phased Power Distribution Upgrades: 

Installed new MCCs and MDPs while analyzing facility loading and existing 480V–120V distribution to strategically replace or refeed panels in a way that improved capacity, aligned with client preferences, and maintained budget considerations.

Operationally Focused Phasing: 

The project was planned around the facility’s equipment and processes, grouping equipment by phase so upgraded areas could run with new automation while the rest of the plant continued operating in its existing configuration. Phase 2 included a planned four-day shutdown to cut over about 30 motors and 50 devices.

Prefabrication & Digital Coordination: 

Utilized prefabricated conduit assemblies, VDC coordination, and Matterport site scans to improve installation efficiency, enhance client collaboration, support estimating and planning, and streamline field execution.