Degumming Process Facility Project

Project Specifications

Industry
Degumming

Dollar Amount
$4,320,000

Completion Date
2013

Location
Midwest
Interstates performed a complete design-build electrical package to upgrade the degumming process facility for the soybean processing facility located in St. Joseph, Missouri. The project scope included electrical engineering, electrical construction, instrumentation, and control systems integration. The project included a remodel of facilities on a three acre site which involved tearing down the old degumming building and constructing a new facility.
Services Provided: Electrical Construction | Electrical Engineering | Instrumentation | Electrical Prefabrication
Key Scope Components
Interstates installed 210,00 feet of wire and 25,000 feet of rigid conduit.
In addition, we installed 140 light fixtures, wired 143 motors, and wired 512 control devices and instruments.