Biofuels Facility Project
Project Specifications
Industry
Biofuels
Dollar Amount
$13,000,000
Completion Date
2019
Location
Wichita, KS
Interstates provided a complete design-build electrical package for a 60MMGPY biodiesel facility located in Wichita, KS. This project displayed excellence on several fronts, including the innovative use of 3D scanning and building information modeling (BIM) and time savings using prefabrication.
Services Provided: Electrical Construction | Electrical Engineering Control Systems | Instrumentation
Key Scope Components
Installed 264,257 Feet of Wire
Installed 28,421 Feet of Basket Tray
Installed 5,121 Feet of Cable Tray
Installed 689 Devices
Wired 1,179 Devices