Boyd Lake Water Treatment Project

Inside view of a wastewater treatment plant.

Interstates’ collaborated with the City of Greeley on updates to its Boyd Lake water treatment plant in Loveland, CO. Working with a local general contractor, Interstates provided electrical construction services on this project. Tight schedules and long lead times caused the project great concerns; however, the team worked together to solve those problems to make up for lost time. One example was using cable tray and cable in place of conduit to save both labor and material costs. Having Interstates’ panel shop fabricate control panels offsite also reduced manhours.

Key Scope Components

Replaced a 75HP variable frequency drive (VFD) for a backwash pump. Replaced antiquated medium voltage switchgear with new medium voltage switchgear.

Learn More